Floor 2 Refurbishment

Update: 09/10/19: What chair?

We are now at the point of preparing to order furniture for floor 2, and we need your help!

Come along to the Library Fair on Tues 15 October 11-3 to try out some possible chairs and desks and let us know what you think.

The furniture samples will be out at one of the stalls on the ground floor of the Library, along with some visualisations of what the floor will look like once the project is complete.

Update: 30/09/19: Power up

Following our power shutdown last Saturday, our contractors are now working on the electrics on floor 2, so that we can ensure power is available to every desk.

Update: 04/09/19: Out with the old and in with the new

As we progress swiftly through August, we’re sure people are eager for updates on the second-floor refurbishment. As some of you will have noticed, contractors are back on the scene tearing up the old carpets (hurrah!), removing all the old tables and chairs and replacing the blinds. Below is a panoramic view of floor 2 with some of the old furnishings remaining, it may be the last view we have of the old floor layout!

Inside of floor 2 with the carpets removed and the space looking empty

In addition, the colour of the new carpet tiles has been chosen. We’ve opted for a mix of sophisticated dark pink, navy and dark grey (“Sakura”, “Inkpot” and “Yari”, for those carpet connoisseurs) which will provide a bit of colour to the floor whilst (hopefully—spillage test coming soon!) remaining encouragingly resistant to stains. These colours beat out worthy contenders “Lantern” (orange) and “Arashi” (light grey), all pictured below for your reference. We eagerly look forward to seeing how work progresses, and opening the new and improved floor 2 when everything is completed.

Man standing on a selection of different coloured carpet tiles

Update: 17/08/2019: The contractors are here

Boarding outside of floor 2's north wing

We had a lot of books to move, but we did it.

Now the contractors are now here and working on the floor and getting it ready. Sorry for any of the noise, we promise it will be worth it!

Update: 19/08/19: Getting ready for the next phase

A contractor has now been appointed to carry out the refurbishment work.

We expect them to start later this week or early next week.

Watch this space for further updates!

Update: 02/07/19: No more shelves

Floor 2 with no shelves

Phase 1 is complete. All of the shelves have now been removed from the floor - see how spacious it looks!

The north wing lift is back in use as normal.

The group study room on floor 2 will remain in use as a temporary book shelving location for the rest of the project.

The Library will be closed this weekend 6-7 July for electrical enabling works to take place.

Floor 2 remains closed and we expect contractors on site in the next couple of weeks to start the next phase.

Update: 25/06/2019: Empty shelves

All of the books have now been cleared from the shelves, and the shelves themselves are in the process of being dismantled. 

The area is closed off and shelves are being dismantled until 28 June.

The group study room on floor 2 is in use as a temporary book shelving location.

The lift in the north wing is currently out of action to Library users until 28 June whilst books and shelves are being moved. There may be some disruption on floor 2 of the north wing during this time and it may be advisable to work elsewhere in the Library during this period.

Update: 18/06/2019: And so it begins

If you've been around the library recently, you may have seen all the moving and shaking on floor 2. We've been busy moving books and getting the space ready to be transformed. We've got a way to go, but wanted to show you some of the work that's been going on in the last week. We moved nearly 50,000 books so far, about 1/3 of the total number on the shelves. Don't forget you can still get hold of them using the store request form, or find them in the floor 2 group study room.